I own land in Pagosa Springs. Now what, and in what order?

​

These are the normal steps from buying a lot to moving into the house, in the order they happen. It's the sequence I walked clients through for thirty years as a builder, and it hasn't changed. What's changed is my part in it: I draw the house now, and your builder builds it.

​

Start with a few facts about the lot​

These basics tell us which codes and restrictions apply to your new house:​

​

Find out what you already have​

If a survey came with the sale, we'll use it. If not, the county's maps will give us the driveway access side, along with the setbacks and the building envelope. The next question is whether anything has already been done on the lot: entry access and a culvert, a driveway, or a cleared home site. A soils test isn't required in Archuleta County, but it can be a good idea depending on the lot. If you want one, this is the time for it, before design.

​

Decide what you want​

Home size, features, views, garages. This is usually when we walk the lot together. We'll look at the slopes, the drainages, the views and the access, and where electric, water and sewer come in or where a septic field can go. We'll talk about where the house gets placed and why, and any advantages or difficulties I see.

​

Design, then the full set​

Design comes first. Then the complete plan set, with engineering where it's required, and the final architectural stamps. Once the plans are complete, or as soon as the foundation plan is, a licensed Colorado surveyor prepares the Proposed Improvement Location Certificate (PILC), which shows the location of the house, driveway, utilities and trees on the lot, and stakes out the house perimeter on the ground.

​

Find your builder​

You can bring a builder in at any point along the way. Once the plans are finished, your contractor will get final bids and give you a price and a building contract.​

Permits, in this order

  1. Water and sewer

  2. Driveway access

  3. HOA approval, which for PLPOA means a submittal and then a meeting

  4. The fire district fee

  5. The county or Town building permit comes last, because the building department wants the rest in hand first

 

Two timing guidelines, with the caveat that they're guidelines: PLPOA reviews plans at meetings twice a month, with a submittal date at least two weeks before the meeting, and the county asks you to allow at least fifteen business days for plan review.​

Turquoise alpine lake reflecting the peaks and snowfields of the San Juan high country in summer

Construction​

This is the general order of construction. It can vary with your project and some of these items are completed simultaneously.​

​

  1. Bids, building contract, then permits

  2. Driveway, utilities, excavation and foundation

  3. Framing

  4. Electrical and plumbing rough-in, then HVAC rough-in

  5. Decking and railing, windows and doors, siding and roofing

  6. Insulation and drywall

  7. Flooring, cabinets, counters, trim and painting

  8. Final electrical and plumbing, then final hardware

  9. Exterior flat concrete, landscaping and the punch list

  10. Final inspections, the Certificate of Occupancy, and you move in

​

Related pages

The 2027 building code changes

Do you need an architect to build a house in Archuleta County?

Water, sewer, well and septic in Pagosa Springs: find out before you buy

​

Where this comes from

Archuleta County Building Department permit packet and submittal requirements. Pagosa Lakes Property Owners Association Environmental Control Committee schedule. Reviewed October 2026.